5X

11/09- Williams Hall/ISB Construction Updates

ISB

Work in Progress

  • Continue pre cast and brick work along G line, lines 8 to 17.

  • Continue curtain wall installation at the east side of the building.

  • Continue monitor framing and glass at the north side of the building.

  • Continue last back filling in the east section of the building.

  • Last hydraulic slab pouring in the east side of the building is in progress.

  • Start slab on grade pouring on the north side, and 2” topping, from lines 1 to 7.

  • Start slab on grade pouring from lines 13 to 17, and 2” topping from lines 7 to 17.

  • Start framing for penthouse panels.

  • Start metal enclosure for stairs #3.

  • Start metal framing along north canopy and line A.

Looking Forward

  • Finalize pre cast and brick work along G line, from lines 8 to 17.

  • Continue metal framing work along north canopy and line A.

  • Continue MEP equipment installation in penthouse.

  • Continue slab on grade pouring at the east side of the building.

  • Continue back filling on the east side of the building.

  • Start metal enclosure for stairs #3.

Williams Hall

Work in Progress

  • Continue concrete final painting on the north side of the building.

  • Continue with CW work in tunnel.

  • Start installation of the mechanical curbs in basement.

  • Start installation of the switch gear in electric room.

Looking Forward

  • Finalize final painting concrete.

  • Continue with steam station work in mechanical room. 

  • Continue with CW work in tunnel.

  • Continue with plumbing underground work.

POSTED: Wednesday, November 9, 2016 01:04 PM
Updated: Saturday, December 3, 2022 01:02 AM