5X社区

2/25- ISB Construction Updates

Work in progress:

  • Augercast pile installation continues in the SE corner of the site.  Currently 315 piles have been installed and 30 remain.
  • Pile cap and grade beam forming and installation has begun.
  • Basement retaining walls forming to begin 2/25/16.
  • Elevator #1 (North) concrete hoistway walls to begin 2/25/16.

Looking Forward:

  • Complete augercast pile installation on 2/29/16.
  • Continue with pile caps and grade beams along column line 'A' (West side).
  • Continue with forming and placement of elevator #1 hoistway walls.
  • Continue with basement retaining walls following behind grade beams along column line 'A' north to south.
POSTED: Thursday, February 25, 2016 03:29 PM
Updated: Saturday, December 3, 2022 01:02 AM