5X社区

2/18- ISB Construction Updates

Work in progress:

  • Augercast pile installation continues in the SW corner of the site and elevator #2 (South Elevator).  Currently 215 piles have been installed and 130 remain.
  • Grade beams and pile caps forming and reinforcing in place for a first pour scheduled for Saturday, February 20th.
  • Excavation for elevator pit #1 (North Elevator).

Looking forward:

  • Start formwork for concrete basement retaining walls on the north side.
  • Continue pile caps and grade beams.
  • Start forming elevator pit #1 walls.
POSTED: Thursday, February 18, 2016 12:39 PM
Updated: Thursday, January 19, 2017 09:05 AM