5X社区

3/11- Cunningham Hall Renovation Update

Work in Progress:

  • Work continues on the chilled water service lines in the 3rd floor east mechanical room.
  • Work continues on the steam service in the 3rd floor west mechanical room.
  • Installation of AHU#1 in the 3rd floor east mechanical room continues.
  • Unit #4 duct tie in is scheduled for 3/14/2016 (7:00am-3:00pm).
  • Demolition of duct banks in utility tunnels continues.
  • Installation of new electrical & tele/data duct banks continues.
  • Mud slabs have been poured in footers and water proofing has begun.
  • Rebar for footers to start on 3/11/2016.
  • Completed the Phoenix air valves control replacements.

Looking ahead:

  • Continue with the installation of AHU#1.
  • Start the piping on the second floor to the new addition.
  • Start the HVAC sheet metal duct on the second floor feeding the addition.
  • Continue footers and foundation walls.
  • Start the elevator pit concrete.
  • Continue with the electrical & tele/data duct banks.
POSTED: Friday, March 11, 2016 12:00 AM
Updated: Saturday, December 3, 2022 01:02 AM