4/21- Cunningham Hall Renovation Updates

Work in Progress:

  • Continuing the steam and condensation piping in the East Mechanical room.
  • Heating and snow melt piping is continuing in the West Mechanical room.
  • Continuing with the chilled water piping in the West mechanical room.
  • Working on plenum duct at AHU-1 in East Mechanical Room.
  • Currently working on fiber data backbone.
  • Currently installing cable tray in tunnel.
  • Waterproofing of south wall continues.
  • CMU and elevator hoistway has begun.

Looking Forward:

  • Final connections to coils and control valves for new AHU-1 in East Mechanical room.
  • Continue chilled water piping in West Mechanical room.
  • Install new roof exhaust curbs.
  • Begin startup of AHU-1 and commissioning.
  • Complete 1st and 2nd floor lab demolition.
  • Complete with stair demolition.
  • Form and pour the west wall on 4/25-4/27.
  • Complete the elevator hoistway.
  • Vac truck to remove the roof ballast from the Cunningham Annex roof on 4/23-4/24
  • Roofing material delivery on 4/26, roofing to start on 4/27.
POSTED: Thursday, April 21, 2016 06:06 PM
Updated: Thursday, January 19, 2017 09:05 AM